TSMC Tried a 24-Hour R&D Schedule. It Lasted Six Months.

台积电:研发靠脑力不靠工时,24 小时“夜猫子”计划仅半年即失败

新闻资讯C1进阶55.7
278 词 2 分钟 41 次阅读

台积电共同营运长秦永沛表示,研发靠思考与判断,延长工时无法提升效率:公司曾在落后追赶阶段推行 24 小时「夜猫子」研发计划,让工程师承担夜间开发任务,结果仅约 6 个月便失败,此后转向「一个团队」协作文化。

Co-COO Y.J. Mii told students that the “Night Owl” programme, which put R&D engineers on overnight work to outrun US rivals, failed in about half a year — because R&D is brain work, not labour.

October 30 — Y.J. Mii, TSMC’s senior vice-president and co-chief operating officer, told a group of university students that extending working hours does not effectively raise R&D efficiency.

He recalled that when TSMC was behind on process technology and anxious to catch international rivals, it tried a 24-hour R&D programme called “Night Owl,” putting R&D engineers on overnight development work in the hope that longer operating hours would produce a technical breakthrough. The programme was declared a failure after only about six months.

According to the Economic Daily News, the thinking inside TSMC at the time was that if its R&D teams worked around the clock while US competitors worked eight-hour days, the company could build a time advantage and catch up.

In practice, the idea did not deliver the expected results. Mii concluded that R&D depends on thinking, judgement and innovation — it is fundamentally “brain work, not labour” — and that simply adding hours does not translate into higher R&D efficiency.

The failure also pushed TSMC to rethink how R&D and manufacturing work together. The old process — R&D finishes developing a process, then hands it to the fab — ran into trouble; over time the company built a “One Team” culture in which R&D and manufacturing work towards shared goals and share responsibility for the outcome.

Mii gave an example: when a new process moves from development to mass production, ramp-up goes more smoothly if the fab is involved in development early and the handover overlap is extended. And when a process problem appears on the line, several teams analysing the root cause together is faster than one department investigating alone.

阅读测验

共 5 道题目

5 题
1.[单选]

What did TSMC’s “Night Owl” programme involve?

2.[单选]

How long did it last?

3.[判断]

Mii concluded that R&D is “brain work, not labour,” so adding hours does not raise efficiency.

4.[多选]

What replaced the old handover model? (Select all that apply)

5.[填空]

Mii gave the advice while speaking to university _____.

(1)

评论

0 条讨论

按时间

登录后发表评论

立即登录

暂无评论

成为第一个分享想法的人吧!